ArithmeticTime & Work, Pipes & Cisterns
A alone can do a piece of work in 21 days. B who is 40% more efficient than A, will finish the work in:
  1. a.10 days
  2. b.12 days
  3. c.15 days
  4. d.18 days

Answer: (C) 15 days

B does 1·4 times A's daily work, so B needs 21 ÷ 1·4 = 15 days. Cutting 40% off A's time gives about 12·6 days, which is the usual trap.